Qalqele gold mine has 71 million tons of proven reserves with a grade of 7.1 grams per ton. Development company
Kurdistan gold mines plan to process 111 thousand tons of ore in 71 years.
have given. The product waste is a dry cake type, which after the filter press should be stored in the waste storage
The face of the dry mass should be piled up. For waste accumulation due to less than 01 ppm of cyanide in the waste,
There is a need for a place that is in a favorable condition in terms of location, slope and environmental issues
should be isolated. Consultant services include basic studies (meteorology, hydrology, geology
and geotechnics) and basic and detailed design of waste substructure, dry mass, transfer system and accumulation of waste,
Water diversion channels, collection channel and contaminated water tank and return water transfer system to
It is a factory.