Projects & Services

Basic & Detail Design, Procurement, and supervision of the Iran Airtour Airlines Hangar at Mashhad Airport

Project: Basic & Detail Design, Procurement, and supervision of the Iran Airtour Airlines Hangar at Mashhad Airport

Client: Iran Airtour Airlines

Background: Iran Airtour Company will construct a
maintenance hangar for the maintenance, repair and overhaul of Airbus A320 and
McDonnell Douglas MD80 aircraft at Mashhad Airport under a 30-year BOT (Build,
Operate, Transfer) contract. The hangar will be built on a 120×150‑meter plot
of land located on the southeastern side of the airport runway.

Actions: Two design options—single‑bay and double‑bay—are being considered. The
hangar interior measures 60×120 meters, with ancillary buildings on three sides
housing repair workshops, storage areas, and administrative and management
offices. The total floor area of the hangar complex is approximately 7,500
square meters and includes the following sections: wheel, tire, and brake
workshops; painting and sandblasting; machining; hydraulics; electromechanics;
battery; seat repair; airborne navigation; ground support equipment; high‑voltage
and low‑voltage switchgear rooms; diesel generators; and transformers. An apron
measuring 120×90 meters is also planned to accommodate light servicing and
quick‑turn checks for up to three aircraft simultaneously.

Results: This hangar, which is the largest of its kind in Khorasan Razavi Province, will not only serve the aforementioned aircraft but will also provide maintenance and repair services for similar aircraft operated by other airlines at Mashhad International Airport. The project is expected to generate direct productive employment for over 150 people, and up to four times that number in indirect jobs.

 

Iran National Copper Industries Company

1. Upgrading the tailings drainage and water supply system of Sarcheshme Copper
2. Field monitoring and measurement of tailings movement in Midok
3. Hydrographic operation of Sarcheshme tailings dam reservoir
4. Improvement of concrete cover of coarse soil storage
5. As Built maps of the water supply system
6. Control and monitoring of water master plan plants
7. Groundwater studies of Khatunabad plain
8. Management of water and tailings of Navchun and Darehazar mine
9. Managing the construction project of Kerman, Rafsanjan and Shahrbabak stadiums
10. Feasibility studies of copper downstream industries
11. Seismic studies, rock mechanics and geotechnics of Darezar concentrator factory
12. Update of underground water studies of Khatunabad plain and Shahrbabak plain
13. Persian Gulf water transmission line and pumping station

1. Upgrading the tailings drainage and water supply system of Midok Copper
2. Studies of water resources and tailings accumulation of Aliabad copper mine
3. Studies of the second phase of Sarchesheme copper concentration development
4. High-level and workshop supervision of the Midok Sedimentation Dam (continuation of 8501)
5. Location studies of Songun copper leaching plant construction project
6. National Administrative and Commercial Tower of Iran’s Copper Industries
7. Water and tailings management of Chelkore mine in Zahedan
8. Copper slag concentrate water and waste management
9. Management of water and tailings of Dareh Alu mine
10. Conducting meteorology and hydrology studies in the area of mines and concentrate factories of Chafirozeh and Ijo
11. Construction of Kerman Stadium
12. Continuation of the water master plan of Sarcheshme Copper Complex, Dere Zar, Shahrbabak, Daralo
13. Improvement of the main water supply network of Sarcheshme copper complex