Arman Flight Catering Building and Installations

Project: Flight Catering Building and Installations

Client: Arman Flight Catering

Background: To expand its catering services in Tehran, Arman Catering Company planned the addition of an annex building to its existing facilities. MEWE was appointed to carry out the design and construction supervision for this brownfield project. The design was developed in accordance with both international and local standards, as well as the client’s specific requirements.

Actions: The extension covered an area of approximately 500 m², built with a steel structure and spans ranging from 7 to 10 meters. The annex was designated for nutrient storage, food preparation, and trolley washing. Performing construction works without disrupting the operations of an active kitchen required the incorporation of additional health and safety measures throughout the project.

Results: The facility’s original production capacity of 15,000 meals per day was increased by 6,000 meals per day with the new extension. Utilities were designed to maximize use of the existing systems, with upgrades made to the sewage network and grease traps to accommodate the increased load.

Iran National Copper Industries Company

1. Upgrading the tailings drainage and water supply system of Sarcheshme Copper
2. Field monitoring and measurement of tailings movement in Midok
3. Hydrographic operation of Sarcheshme tailings dam reservoir
4. Improvement of concrete cover of coarse soil storage
5. As Built maps of the water supply system
6. Control and monitoring of water master plan plants
7. Groundwater studies of Khatunabad plain
8. Management of water and tailings of Navchun and Darehazar mine
9. Managing the construction project of Kerman, Rafsanjan and Shahrbabak stadiums
10. Feasibility studies of copper downstream industries
11. Seismic studies, rock mechanics and geotechnics of Darezar concentrator factory
12. Update of underground water studies of Khatunabad plain and Shahrbabak plain
13. Persian Gulf water transmission line and pumping station

1. Upgrading the tailings drainage and water supply system of Midok Copper
2. Studies of water resources and tailings accumulation of Aliabad copper mine
3. Studies of the second phase of Sarchesheme copper concentration development
4. High-level and workshop supervision of the Midok Sedimentation Dam (continuation of 8501)
5. Location studies of Songun copper leaching plant construction project
6. National Administrative and Commercial Tower of Iran’s Copper Industries
7. Water and tailings management of Chelkore mine in Zahedan
8. Copper slag concentrate water and waste management
9. Management of water and tailings of Dareh Alu mine
10. Conducting meteorology and hydrology studies in the area of mines and concentrate factories of Chafirozeh and Ijo
11. Construction of Kerman Stadium
12. Continuation of the water master plan of Sarcheshme Copper Complex, Dere Zar, Shahrbabak, Daralo
13. Improvement of the main water supply network of Sarcheshme copper complex